The Rook
Completed Works During May 2026 (The Rook)
Completion of plastering and rendering works for the entire building
Completion of 50% of the aluminum facade installation works
Current Ongoing Works
First: Plastering & Rendering Works
Ongoing execution and completion of plastering works across all project floors
Second: Painting & Finishing Works
Painting works are currently underway on different floors
Continuation of putty application and surface preparation for final painting works
Ongoing internal finishing works throughout all project floors
Third: Flooring Works (Marble)
Continued supply and delivery of the project’s marble materials
Execution of marble flooring works on several floors
Fourth: Facades & Aluminum Works
Ongoing completion of aluminum works installation for the glass facades
Continued façade installation works in accordance with the approved design
Completion of aluminum façade material delivery in preparation for the installation of the external glazing
Fifth: Doors & Duct Works
Continuation of door and duct frame fixing works on various floors