Mazaya Developments

The Rook

Progress rate
75%

Completed Works During May 2026 (The Rook)

Completion of plastering and rendering works for the entire building

Completion of 50% of the aluminum facade installation works

Current Ongoing Works

First: Plastering & Rendering Works

Ongoing execution and completion of plastering works across all project floors

Second: Painting & Finishing Works

Painting works are currently underway on different floors

Continuation of putty application and surface preparation for final painting works

Ongoing internal finishing works throughout all project floors

Third: Flooring Works (Marble)

Continued supply and delivery of the project’s marble materials

Execution of marble flooring works on several floors

Fourth: Facades & Aluminum Works

Ongoing completion of aluminum works installation for the glass facades

Continued façade installation works in accordance with the approved design

Completion of aluminum façade material delivery in preparation for the installation of the external glazing

Fifth: Doors & Duct Works

Continuation of door and duct frame fixing works on various floors

 

Contact Us