Gemini Blue

Progress rate
40%

Completed Works During May 2026 (Gemini Blue)

Completion of the first floor concrete works

Current Ongoing Works

Continuation of formwork works and layout marking for the first floor vertical structural elements

Ongoing completion of internal core wall formwork cladding works

Ongoing lifting and installation of steel reinforcement for the first floor vertical elements

Commencement of steel reinforcement works for the first floor vertical structural elements

Commencement of formwork works for the first floor vertical elements, along with layout marking and surveying point setting