Gemini Blue
Progress rate
40%
Dear Valued Clients of Gemini Blue 😊,
We would like to update you on the latest engineering and construction progress at the project in accordance with the current work schedule:
First: Waterproofing & Basement Works
- Ongoing completion of surface preparation works prior to waterproofing for the front basement retaining wall
- Ongoing completion of masonry works for the left-side wall of the first basement level
Second: First Basement Slab Works
- Continuation of carpentry and steel reinforcement works for the first basement slab
- Installation of first basement slab beams and continuation of reinforcement works
- Continuation of reinforcement and formwork works for the building core
- Execution of the first reinforcement layer works and completion of the first basement slab preparations
- Steel material stockpiling in preparation for concrete casting works
- Completion of the remaining concrete casting works for the first basement slab 🙏
Third: Ground Floor Works
- Ongoing reinforcement and formwork works for the ground floor vertical structural elements
Fourth: Plaza Works
- Completion of the first basement plaza concrete casting
We would like to assure you that all works are progressing according to the approved project timeline and at steady execution rates, while maintaining the highest quality standards. We will continue to keep you updated with all new developments on a regular basis.
Thank you always for your trust.