Gemini Red
Progress rate
50%
Completed Works During May 2026 (Gemini Red)
Completion of the seventh floor concrete works
Current Ongoing Works
Ongoing layout and marking works for the seventh floor vertical structural elements
Ongoing formwork and steel reinforcement works for the seventh floor vertical elements
Continuation of structural works on the upper floors in accordance with the approved project schedule