The Rook
Progress rate
75%
Dear Valued Clients of The Rook 😊,
We would like to update you on the latest engineering and construction progress at the project in accordance with the current work schedule:
First: Plastering & Rendering Works
- Ongoing execution and completion of plastering works across all project floors
- Noticeable progress in rendering works at various levels of the project
Second: Painting & Finishing Works
- Painting works are currently underway on different floors
- Continuation of putty application and surface preparation for final painting works
- Ongoing internal finishing works throughout all project floors
Third: Flooring Works (Marble)
- Continued supply and delivery of the project’s marble materials
- Execution of marble flooring works on several floors
Fourth: Facades & Aluminum Works
- Ongoing installation of aluminum and glass façade systems
- Continued façade installation works in accordance with the approved design
Fifth: Doors & Duct Works
- Completion of door and duct frame fixing works on various floors
- Work progress is proceeding according to the approved project schedule
We would like to assure you that all works are progressing steadily and in line with the approved timeline, while maintaining the highest quality standards. We will continue to keep you updated with all new developments on a regular basis.
Thank you always for your trust.